The short version
Damac Group chairman Hussain Sajwani says about $9 billion of the group's $20 billion US data centre pledge has now been invested, with the rest tied to land and power. He warned that building costs, already up around 30 percent, could climb further, and a global index shows the same pressure well beyond the UAE.
What happened
Hussain Sajwani, the founder and chairman of Damac Group, spoke at Bloomberg Invest Dubai 2026 about the group's push into data centres (large buildings full of computers that run cloud services and AI tools). He said around $9 billion of the $20 billion the group committed to the United States has been invested, AGBI reports. The rest will follow as suitable land and power become available, according to WAM, the UAE's state news agency.
Sajwani said data centre building costs have gone up by around 30 percent and could rise by a further 20 to 30 percent, WAM and GDN Online report. He named the United States and Europe among the dearest places to build, with Asian markets cheaper on labour and equipment. The bigger problem, he said, is not cost alone but supply-chain disruption and repeated delays in getting the equipment needed to finish projects.
Damac focuses on large sites starting at around 100MW (megawatts, a measure of how much power a site can draw), cooled mainly by liquid to handle AI chips. Its data centre arm, Damac Digital, has around 6GW of planned capacity, and Sajwani wants that to reach 10GW by the end of 2027, GDN Online reports.
The background
Sajwani first set out the $20 billion US plan in Florida in January 2025, with US president Donald Trump present, AGBI notes. In January this year Menatech reported that Damac had secured US land and power worth $12 billion, in Ohio and New Jersey, with sites in Texas under review. Menatech said the full programme could take 2 to 4 years to reach its target.
The cost pressure is not unique to Damac. Turner & Townsend's Data centre construction cost index 2026-27, drawn from over 500 projects in 62 markets, finds average cost per watt up 13% year on year in North American and European markets. It says 52% of industry leaders it surveyed saw cost inflation of between 6 and 15% in 2026, and 81% say skilled labour in their region is constrained.
The AI angle
These buildings exist because of AI. Turner & Townsend says AI is speeding up demand for computing power and changing how data centres are built. In the United States, data centres made for AI workloads cost around 10% more than traditional ones, because they pack equipment more densely, need liquid cooling and are built to tighter deadlines. The most advanced AI sites cost between US$14.00 and US$16.00 per watt to build, against a US$12.08 country average.
Sajwani is also on the other side of the AI trade. WAM reports he told the Dubai audience that his holdings in OpenAI, SpaceX and Anthropic have already earned him billions of dollars. For a business that rents AI tools, the link is direct: every AI assistant or agent runs on computers in buildings like these, and Sajwani said higher building costs can be handled through pricing models and contracts with major corporate customers.
What it means for owners and operators
The cost of building the places where AI runs is rising, not falling. Builders say they will pass that on through contracts with their biggest customers, the cloud companies. Those firms in turn sell AI tools and computing time to businesses of every size.
For a small firm that does not mean AI will suddenly cost more next month. It does mean the price of AI tools has a floor set by concrete, cooling and power, and suppliers may have room to raise prices when contracts renew. Delays in getting equipment can also limit how fast new capacity arrives.
Our take
Our view, drawn from the reporting in this story. It is analysis, not news.
We think the common idea that AI only gets cheaper misses half the picture. The AI tools themselves may get more efficient, but the buildings that run them cost around 30 percent more to put up, by Damac's account, and an industry index shows the same rise in North America and Europe.
A business planning to lean on AI agents should treat computing as a cost that can go up, and build that into contracts and budgets now. Firms that lock in clear prices, and know what they would cut if bills rose, will be in a better place than those that assume today's price lasts.
The numbers
Damac has invested about $9 billion of its $20 billion US commitment, and its building costs are up around 30 percent, while US data centres for AI cost around 10% more to build.
US commitment
Rise in building costs
What to do in your business tomorrow
- Check each AI and cloud contract your business holds for clauses that let the supplier raise prices before the term ends, and note the renewal dates.
- Work out what your monthly AI tool bill would be if it rose sharply at your next renewal, and decide now which tools you would keep and which you would drop.
- Ask your cloud supplier which country your AI tools run in, because building costs differ widely from one market to another.
Related coverage
Sources
- AGBI: Rising costs complicate Damac's $20bn US data centres plan
- Menatech: Damac secures $12 billion in land and power for its data center expansion in the United States
- WAM: DAMAC targets 10GW global data-centre capacity by end-2027
- GDN Online: DAMAC targets 10GW global data centre portfolio by 2027 end
- Turner & Townsend: Data centre construction cost index 2026-27